Lower Likhu Hydropower

Project Lower Likhu Hydropower Project (28.1 MW)
Location Ramechhap (Left Bank)/ Okhaldhunga (Right Bank)
Client Swet Ganga Hydropower & Construction Ltd.
Civil Contractor High Himalaya Hydro-Bavari Construction JV (Joint Venture Between High Himalaya Hydro Construction Pvt. Ltd. & Bavari Construction Pvt. Ltd.)
Works All Civil Works:
Weir: Type: Boulder Lined, Crest Elevation: 725.00m, Length: 47m, Height: 8.15m (from foundation), 6m (from river bed)
Undersluice: 2 nos, 6.0m x 6.0m
Intake: Type: Side Intake, No. of Openings: 3, 4.5m x 2.85m (each opening)
Gravel Trap: Type: Surface, 8m x 4.5m x 1.9m
Settling Basin: Type: Surface, 3 nos, 12m x 12.5m x 7m
Headrace Pipe: Diameter: 3.75m, Thickness: 8-10mm, Length:1285m
Headrace Tunnel: Inverted D-shape, Length: 3600m, Diameter: 5m
Surge Tank: Height: 29m (from invert), Diameter: 15.40m
Penstock: Vertical and horizontal shaft length: 280m, Diameter: 3.75m, Thickness: 8-25mm
Powerhouse: Type: Semi-Surface, 27.3m x 22.0m x 24.47m
Tailrace Culvert: Length: 125m, Height: 3.55m, Width: 3.55m
Status 5% completed